/Armour Road between Clifton Street and Hunter Street will be closed to through traffic, with access maintained for local traffic, during a major infrastructure project that will include replacing storm sewers, sanitary sewers and the water main as well as road reconstruction.
Local traffic with a destination within the road closure will be permitted, however travellers may experience delays within the construction limits.
The project, awarded to Green Infrastructure Partners Inc., is tentatively scheduled to begin on July 17. The majority of the work is scheduled to be completed by late fall of 2023. Any carryover work that remains will be completed between May and July 2024.
The project includes removal of existing infrastructure, excavation and grading, installation of new storm sewers and sanitary sewers, watermain, concrete curb and gutter, road base and asphalt, streetlights, sidewalk, tree planting, pavement markings and regulatory signage.
Detour routes:
Vehicle detours
Southbound traffic will turn west at Parkhill Road East, south on George Street and east on Hunter Street to Armour Road.
Northbound Traffic will travel west on Hunter Street, north on Water Street and east on Parkhill Road to Armour Road.
Pedestrian detours
Pedestrians travelling north and south will take Rogers Street between Hunter Street and Hazlitt Street.
Transit detours
Peterborough Transit Route 7 will be rerouted northbound, continuing straight on Rogers Street, turning right on Dufferin Street and left on Armour Road, returning to the regular route.
Northbound stops on Armour Road at Douro Street, Macfarlane Street and Euclid Avenue will not be served by Route 7 Lansdowne during this construction.
The following temporary bus stops will be added:
Northbound on Rogers Street at Oxford Street
Dufferin Street at Armour Road