The project will include new storm sewers, sanitary sewers, watermain, concrete curb and gutter, road base and asphalt road structure, traffic signals, streetlights, sidewalk, tree plantings, pavement markings, installation of multi-use trails and regulatory signage as part of a full scope road and intersection reconstruction.
During construction Lansdowne Street will be reducedto three lanes; one eastbound lane, one westbound lane and one shared left turn lane.
Clonsilla Avenue will also be reduced to three lanes; one southbound right turn lane, one southbound shared through and left turn lane and one northbound lane.
There is a scheduled road closure of Clonsilla Avenue for the purpose of milling and paving operations near the end of construction. The milling and paving is expected to take four days. As a result, it is expected that local traffic may experience delays within the construction limits.
Dufferin Construction will be completing the project.
The work is scheduled to be completed by late fall 2022.